Giving you control

Projects

Kusile Power Station

Turnstiles for Kusile Power Station

The Situation

Established in 1990, Turnstar is the largest manufacturer of physical access control products in Africa. Turnstar manufactures a full range of turnstiles, revolving doors, man-trap cubicles, vehicle barriers, spike barriers and anti-terror hydraulic bollards and road blockers. All Turnstar products are manufactured at its modern facility in Wynberg, Johannesburg and are exported worldwide. Products are supplied to factories, warehouses, office parks, health clubs, shopping centres, banks, stadiums, power stations and construction sites.

kusile-power-station

Construction of the Kusile coal-fired power station in Mpumalanga is well under way and work is being carried out at a furious pace. The first power generating unit is expected to go online in 2014 and this additional capacity is desperately needed to relieve the Eskom grid which is currently under tremendous strain. All six power generating units are planned to be operational by the end of 2018 with a total capacity of 4800 megawatts.

The Kusile site is approximately 5200 hectares and clearing of the site began in April 2008. The power station is expected to use up to 17 million tons of coal per annum for a period of 47 years. This makes Kusile one of the biggest coal fired power stations in the world.

The problems

A consortium of large construction companies is working on the Kusile project. Stefanutti Stocks, Basil Read, Group Five and WBHO were jointly awarded the civil works contract. Securing a site of this magnitude has been a major challenge.
Over 15000 workers arrive at the main gate every day. Any turnstile solution must not become a bottleneck where unproductive time is wasted whilst waiting to enter the construction site.
Administratively, there is the challenge of accurately managing employee clocking and avoiding time & attendance fraud.
Occupational health & safety is a serious legal requirement and no worker can be allowed onto the site if intoxicated and without the correct PPE.
Opportunities for industrial espionage must be limited. The power generation industry is dominated by American, French and Japanese firms. Each firm has its own industrial secrets and technologies which give it a competitive advantage. No cameras can be allowed into the construction site.
A construction site, by its very nature, is a fluid and temporary arrangement. An area which is a convenient entrance one day can become an obstacle on another day. A temporary access controlled solution would be required which can be easily moved and positioned.

The preparation

Turnstar worked closely with the Eskom management at Kusile to find the right temporary access controlled solution. Turnstar suggested that a bank of turnstiles be installed in converted shipping containers. Recently, Turnstar supplied 48 TITAN half height turnstiles which were installed in containers to the construction site of the London Olympic Stadium. The containers would be fitted with their own DB board and all access control paraphernalia required for time & attendance.

The solution

kusile

Eskom placed an order with Turnstar for 56 TRIUMPH 4 full height single turnstile and 7 forty foot shipping containers. The TRIUMPH was chosen due to its durability in harsh and dusty environments. It is also supplied with an industry leading 5 year guarantee. Each container would be fitted with 8 turnstiles. 15000 employees will be using these turnstiles, which means +/- 270 employees per turnstile. On average, it would take 30 minutes for all employees to enter the construction site, which is within Eksom’s requirements. Before entry through the turnstile, all employees are checked for intoxication by means of an alcohol sniffer and are checked for cameras.

The shipping containers were waterproofed, painted and converted by removing the side panels. The removal of the side panels creates a large entrance through which the employees can pass through the 8 turnstiles. Lighting and an Eskom approved DB board were fitted. The turnstiles were bolted to the wooden floor. Once completed, the containers were taken from the depot through to Kusile by means of a crane truck. The crane then placed the container at the area to be access controlled.

The project took a total of 8 weeks from date of order to final delivery to complete.

Fact file

Project: Supply of 56 TRIUMPH full height turnstiles in 7 forty foot converted shipping containers

Customer: Eskom Kusile Power Station

Project timeline: 8 weeks

SEND US A MESSAGE

COVID-19 Range Available

Our Covid-19 range is now available. Ensure a safe working environment during the Covid-19 outbreak.